Sewer Extension Lower Cove Road Sewer Phase 2
McIvers, Newfoundland and Labrador
Federal contribution
$324,471
Federal share36%
of $906.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 16, 2020
20212022
Built
Approved 7 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of McIvers
- Construction start
- Aug 3, 2021(actual)
- Construction end
- Jul 11, 2022(actual)
Against the original forecast
- Construction end7 months lateforecast Nov 30, 2021