Main Street Water and Sewer Phase II

Eastport, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$210,753
Federal share40%

of $526.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 15, 2021
20212022
Built

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Salvage
Construction start
Jun 13, 2022(actual)
Construction end
Sep 9, 2022(actual)

Against the original forecast

  • Construction end7 months earlyforecast Mar 31, 2023

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56907 in the federal list. How to read these figures.