Schedule

Announced and approvedAug 4, 2020
20212022
Built

Approved 3 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
City of Summerside
Construction start
Jun 7, 2021(actual)
Construction end
Feb 24, 2022(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Jan 28, 2022