MiWay Stop Marker Signs and Light Rail Transit (LRT) Digital Sign Provisions

Mississauga, Ontario

underwayPublic TransitPTIS
Federal contribution
$161,600
Federal share40%

of $404.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 21, 2021
today
2021202320252027
BuiltForecast

Approved 7 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of Mississauga
Construction start
Apr 8, 2024(actual)
Construction end
Mar 31, 2028(forecast)