Upgrade of Drinking Water Treatment Facility
Federal contribution
$440,800
Federal share40%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
today
2021202320252027
BuiltForecast
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Pointe-des-Cascades
- Construction start
- Jun 4, 2020(actual)
- Construction end
- Dec 1, 2027(forecast)
Against the original forecast
- Construction start7 months earlyforecast Jan 4, 2021
Also in Pointe-des-Cascades
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56984 in the federal list. How to read these figures.