Upgrade of Drinking Water Treatment Facility

Pointe-des-Cascades, Quebec

underwayDrinking WaterGIS
Federal contribution
$440,800
Federal share40%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
today
2021202320252027
BuiltForecast

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Pointe-des-Cascades
Construction start
Jun 4, 2020(actual)
Construction end
Dec 1, 2027(forecast)

Against the original forecast

  • Construction start7 months earlyforecast Jan 4, 2021