North Coast - ChargeNorth Level 2 EV Charging Network for North and Central BC

North Coast, British Columbia

completeGreen EnergyGIS
Federal contribution
$414,800
Federal share40%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2020
2021202220232024
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Sep 1, 2022(actual)
Construction end
Aug 31, 2024(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 1, 2022
  • Construction end3 months earlyforecast Nov 30, 2024

Also in North Coast