Kanaka Bar Indian Band - Energy Self-Sufficient Affordable Housing Development - the Crossing Place

Kanaka Bar, British Columbia

completeGreen EnergyGIS
Federal contribution
$330,505
Federal share75%

of $440.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2020
202120222023
Built

Approved 2 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Kanaka Bar Indian Band
Construction start
Aug 5, 2022(actual)
Construction end
May 31, 2023(actual)

Against the original forecast

  • Construction end18 months earlyforecast Dec 1, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57003 in the federal list. How to read these figures.