Canada Games 2023 Credit Union Place Athlete Training & Hosting Upgrades
Summerside, Prince Edward Island
Federal contribution
$180,000
Federal share40%
of $450.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 4, 2020
2021
Built
Approved 8 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Summerside
- Construction start
- Sep 23, 2020(actual)
- Construction end
- Mar 26, 2021(actual)
Against the original forecast
- Construction start8 months earlyforecast Jun 1, 2021
- Construction end5 months earlyforecast Aug 31, 2021