Rugby Nova Scotia - Graves Oakley Field Clubhouse
Federal contribution
$420,000
Federal share28%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 9, 2020
20212022
Built
Approved 3 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Halifax Tars Rugby Football Club
- Construction start
- May 24, 2021(actual)
- Construction end
- May 4, 2022(actual)
Against the original forecast
- Construction end3 months lateforecast Jan 31, 2022
Also in Halifax