Forestville Port Facilities Rehabilitation
Federal contribution
$1.4M
$1,421,346
Federal share17%
of $8.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 12, 2021
202120222023
Built
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Forestville
- Construction start
- Feb 13, 2023(actual)
- Construction end
- Oct 16, 2023(actual)
Against the original forecast
- Construction end8 weeks lateforecast Aug 21, 2023
Also in Forestville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57073 in the federal list. How to read these figures.