Department of Transportation and Infrastructure - Vaughan Creek Bridge Replacement
Federal contribution
$1.6M
$1,590,500
Federal share30%
of $5.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 10, 2021
20212022
Built
Approved 7 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- New Brunswick Department of Transportation and Infrastructure
- Construction start
- Sep 20, 2021(actual)
- Construction end
- Oct 21, 2022(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 28, 2021
- Construction end2 months earlyforecast Dec 31, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57074 in the federal list. How to read these figures.