Department of Transportation and Infrastructure - Vaughan Creek Bridge Replacement

St. Martins, New Brunswick

completeHighways and RoadsRNIS
Federal contribution
$1.6M
$1,590,500
Federal share30%

of $5.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 10, 2021
20212022
Built

Approved 7 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Sep 20, 2021(actual)
Construction end
Oct 21, 2022(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 28, 2021
  • Construction end2 months earlyforecast Dec 31, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57074 in the federal list. How to read these figures.