Town of Assiniboia & District Recreation Complex
Federal contribution
$6.3M
$6,293,010
Federal share40%
of $15.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 20, 2022
20212022
Built
Approved 21 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Assiniboia
- Construction start
- Apr 1, 2021(actual)
- Construction end
- Oct 26, 2022(actual)
Also in Assiniboia
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57135 in the federal list. How to read these figures.