Rural Municipality of Barrier Valley No. 397 - Archerwill Lagoon Expansion
Rural Municipality of Barrier Valley, Saskatchewan
Federal contribution
$284,950
Federal share40%
of $712.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 9, 2021
20212022202320242025
Built
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Barrier Valley
- Construction start
- Jul 17, 2023(actual)
- Construction end
- Sep 15, 2025(actual)
Against the original forecast
- Construction start7 weeks earlyforecast Sep 1, 2023
- Construction end6 months lateforecast Mar 31, 2025
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57140 in the federal list. How to read these figures.