Back to projects

Beechville Lakeside Timberlea Community Centre

Halifax, Nova Scotia

completeRecreationCCRIS
Federal contribution
$4.0M
$3,960,000
Federal share17%

of $23.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 15, 2020
202120222023202420252026
Built

Approved 5 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Apr 25, 2024(actual)
Construction end
Mar 17, 2026(actual)

Against the original forecast

  • Construction start4 months lateforecast Jan 8, 2024
  • Construction end2 weeks lateforecast Feb 28, 2026

Also in Halifax