Horizon Achievement Centre

Cape Breton, Nova Scotia

completeRecreationRNIS
Federal contribution
$2.7M
$2,680,000
Federal share40%

of $6.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 28, 2020
20212022
Built

Approved 7 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Horizon Achievement Centre
Construction start
Sep 28, 2020(actual)
Construction end
Mar 18, 2022(actual)

Against the original forecast

  • Construction start3 months lateforecast Jul 6, 2020
  • Construction end7 weeks lateforecast Jan 31, 2022

Also in Cape Breton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57158 in the federal list. How to read these figures.