Brigadoon Village Phase II
Federal contribution
$3.0M
$3,000,000
Federal share30%
of $9.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 5, 2020
20212022
Built
Approved 8 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Brigadoon Village
- Construction start
- Dec 28, 2020(actual)
- Construction end
- Jul 29, 2022(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Jan 18, 2021
- Construction end4 weeks lateforecast Jun 30, 2022
Also in Kings
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57160 in the federal list. How to read these figures.