Brigadoon Village Phase II

Kings, Nova Scotia

completeCultureRNIS
Federal contribution
$3.0M
$3,000,000
Federal share30%

of $9.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 5, 2020
20212022
Built

Approved 8 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Brigadoon Village
Construction start
Dec 28, 2020(actual)
Construction end
Jul 29, 2022(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Jan 18, 2021
  • Construction end4 weeks lateforecast Jun 30, 2022