Village of Theodore Water Treatment Plant Upgrade
Federal contribution
$215,246
Federal share40%
of $538.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 9, 2021
2021202220232024
Built
Approved 6 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Theodore
- Construction start
- Jun 13, 2022(actual)
- Construction end
- Nov 16, 2023(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 2, 2022
- Construction end6 weeks earlyforecast Dec 31, 2023