Village of Pilger Water Treatment Plant Upgrade
Federal contribution
$170,400
Federal share40%
of $426.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2021
2021202220232024
Built
Approved 7 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Pilger
- Construction start
- Oct 3, 2023(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction start13 months lateforecast Aug 31, 2022
- Construction end3 months earlyforecast Mar 31, 2024