Pesakastew Solar
Federal contribution
$3.5M
$3,500,000
Federal share75%
of $4.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2021
20212022
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Red Dog Holdings Ltd.
- Construction start
- May 10, 2021(actual)
- Construction end
- Aug 12, 2022(actual)
Against the original forecast
- Construction start3 months lateforecast Feb 1, 2021
- Construction end2 months lateforecast Jun 10, 2022
Also in Weyburn No. 67
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57198 in the federal list. How to read these figures.