Pesakastew Solar

Weyburn No. 67, Saskatchewan

completeGreen EnergyGIS
Federal contribution
$3.5M
$3,500,000
Federal share75%

of $4.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2021
20212022
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Red Dog Holdings Ltd.
Construction start
May 10, 2021(actual)
Construction end
Aug 12, 2022(actual)

Against the original forecast

  • Construction start3 months lateforecast Feb 1, 2021
  • Construction end2 months lateforecast Jun 10, 2022

Also in Weyburn No. 67

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57198 in the federal list. How to read these figures.