Village of Consul's Water Treatment Plant Upgrade
Federal contribution
$390,000
Federal share40%
of $975.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 9, 2021
202120222023
Built
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Consul
- Construction start
- Jul 1, 2022(actual)
- Construction end
- Sep 29, 2023(actual)