2020/21 TIE Local Roads 3

Undefined, Prince Edward Island

completeHighways and RoadsRNIS
Federal contribution
$559,577
Federal share38%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 9, 2021
2021
Built

Approved 6 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Jun 30, 2020(actual)
Construction end
Nov 17, 2020(actual)

Against the original forecast

  • Construction start2 months earlyforecast Sep 1, 2020
  • Construction end7 weeks lateforecast Sep 30, 2020

Also in Undefined

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57294 in the federal list. How to read these figures.