Back to projects

Stormwater Management (SWM) Infrastructure Remediation

Whitesand First Nation, Ontario

underwayWastewaterGIS
Federal contribution
$2.2M
$2,220,200
Federal share75%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2021
today
2021202320252027
BuiltForecast

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Whitesand First Nation
Construction start
Jan 8, 2024(actual)
Construction end
Oct 31, 2026(forecast)