Stormwater Management (SWM) Infrastructure Remediation
Whitesand First Nation, Ontario
Federal contribution
$2.2M
$2,220,200
Federal share75%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 18, 2021
today
2021202320252027
BuiltForecast
Approved 6 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Whitesand First Nation
- Construction start
- Jan 8, 2024(actual)
- Construction end
- Oct 31, 2026(forecast)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57296 in the federal list. How to read these figures.