Wastewater Treatment Plant Upgrades Phase 1 - Replacement of Rotating Biological Contactors
Federal contribution
$2.1M
$2,064,752
Federal share75%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 18, 2021
today
2021202320252027
BuiltForecast
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Wikwemikong First Nation
- Construction start
- Oct 3, 2022(actual)
- Construction end
- Oct 30, 2026(forecast)
Also in Wikwemikong