Sewage Pumping Station Rehabilitation

Weenusk First Nation, Ontario

completeWastewaterGIS
Federal contribution
$451,970
Federal share75%

of $602.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2021
202120222023
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Weenusk First Nation
Construction start
Jun 1, 2022(actual)
Construction end
Aug 15, 2023(actual)

Against the original forecast

  • Construction end8 months earlyforecast Mar 31, 2024