Zhiibaahaasing Water Storage and Distribution System Upgrades
Zhiibaahaasing First Nation, Ontario
Federal contribution
$2.0M
$2,009,388
Federal share75%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 18, 2021
today
2021202320252027
BuiltForecast
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Zhiibaahaasing First Nation
- Construction start
- Feb 24, 2025(actual)
- Construction end
- Dec 28, 2026(forecast)
Also in Zhiibaahaasing First Nation