Water Distribution Renewal and Fire Protection Upgrades

Iskatewizaagegan #39 Independent First Nation, Ontario

completeDrinking WaterGIS
Federal contribution
$1.3M
$1,322,210
Federal share75%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2021
2021202220232024
Built

Approved 8 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Sep 20, 2023(actual)
Construction end
Sep 4, 2024(actual)

Against the original forecast

  • Construction end11 months earlyforecast Jul 31, 2025