RM of Preeceville No. 334, Hinchliffe Bridge Replacement
Preeceville No. 334, Saskatchewan
Federal contribution
$166,650
Federal share17%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 9, 2021
20212022
Built
Approved 5 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Preeceville No. 334
- Construction start
- Dec 1, 2021(actual)
- Construction end
- Feb 16, 2022(actual)
Against the original forecast
- Construction start4 weeks lateforecast Nov 1, 2021
- Construction end6 weeks earlyforecast Mar 31, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57366 in the federal list. How to read these figures.