Back to projects

Rural Municipality of Silverwood No. 123, Grid 703 Bridge Replacement

Silverwood No. 123, Saskatchewan

completeHighways and RoadsRNIS
Federal contribution
$97,993
Federal share17%

of $588.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 9, 2021
2021
Built

Approved 5 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Jun 15, 2021(actual)
Construction end
Jul 9, 2021(actual)

Against the original forecast

  • Construction start5 months lateforecast Jan 1, 2021
  • Construction end6 months earlyforecast Dec 31, 2021

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57368 in the federal list. How to read these figures.