RM of Wood River No. 74, Pinto Bridge Replacement
Wood River No. 74, Saskatchewan
Federal contribution
$166,650
Federal share17%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 9, 2021
20212022
Built
Approved 2 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Wood River No. 74
- Construction start
- Oct 1, 2021(actual)
- Construction end
- Mar 31, 2022(actual)
Against the original forecast
- Construction start11 months lateforecast Nov 2, 2020
- Construction end4 weeks lateforecast Feb 28, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57369 in the federal list. How to read these figures.