RM of Wood River No. 74, Pinto Bridge Replacement

Wood River No. 74, Saskatchewan

completeHighways and RoadsRNIS
Federal contribution
$166,650
Federal share17%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 9, 2021
20212022
Built

Approved 2 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Oct 1, 2021(actual)
Construction end
Mar 31, 2022(actual)

Against the original forecast

  • Construction start11 months lateforecast Nov 2, 2020
  • Construction end4 weeks lateforecast Feb 28, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57369 in the federal list. How to read these figures.