Village of Odessa Community Hall
Federal contribution
$246,016
Federal share40%
of $615.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 9, 2021
20212022202320242025
Built
Approved 3 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Village of Odessa
- Construction start
- Jul 1, 2022(actual)
- Construction end
- Dec 19, 2024(actual)
Against the original forecast
- Construction start9 months lateforecast Oct 1, 2021
- Construction end3 weeks lateforecast Dec 1, 2024
Also in Odessa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57370 in the federal list. How to read these figures.