Village of Fillmore Skating Arena Revitalization
Federal contribution
$79,480
Federal share40%
of $198.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 9, 2021
2022
Built
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Village of Fillmore
- Construction start
- Mar 31, 2021(actual)
- Construction end
- Feb 28, 2022(actual)
Against the original forecast
- Construction start4 months lateforecast Nov 30, 2020
- Construction end8 weeks lateforecast Dec 31, 2021
Also in Fillmore
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57375 in the federal list. How to read these figures.