Northern Village of Denare Beach Community Hockey Bunk Revitalization
Federal contribution
$26,886
Federal share40%
of $67.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 9, 2021
202120222023
Built
Approved 3 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Northern Village of Denare Beach
- Construction start
- Sep 15, 2022(actual)
- Construction end
- Mar 15, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 15, 2022
- Construction end2 weeks earlyforecast Mar 31, 2023
Also in Denare Beach
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57384 in the federal list. How to read these figures.