RM of Torch River No. 488, Canyon on White Fox Grid Culvert Replacement
Torch River No. 488, Saskatchewan
Federal contribution
$36,652
Federal share17%
of $220.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 13, 2021
20212022
Built
Approved 9 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Torch River No. 488
- Construction start
- Aug 19, 2022(actual)
- Construction end
- Oct 3, 2022(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jul 1, 2022
- Construction end4 weeks earlyforecast Oct 30, 2022
Also in Torch River No. 488
- Rural Municipality of Torch River No. 488 - Installation of Culverts on Various Locations$176.9K
- Rural Municipality of Torch River No. 488 - Construction of Bridge, South of Garrick$166.7K
- Bisset Creek Bridge over Bisset Creek in the Rural Municipality of Torch River No. 488$142.4K
- Restoration of Coleman Bridge - Regional Municipality of Torch River$108.2K
- Rural Municipalilty of Torch River No. 488 - Garrick Landfill Decommissioning$53.2K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57388 in the federal list. How to read these figures.