Village of Kenaston - Lift Station Upgrade

Kenaston, Saskatchewan

completeWastewaterGIS
Federal contribution
$174,200
Federal share40%

of $435.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 9, 2021
202120222023
Built

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Kenaston
Construction start
Nov 8, 2021(actual)
Construction end
Jun 8, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast Aug 15, 2021
  • Construction end6 months lateforecast Dec 15, 2022