Boreal Area Regional Waste Authority Inc.- Boreal Area Regional Waste Authority (BARWA) Historical Landfill Site Decommissioning
Federal contribution
$1.4M
$1,421,742
Federal share40%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 23, 2021
202120222023202420252026
Built
Approved 9 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Nipawin
- Construction start
- Aug 5, 2024(actual)
- Construction end
- May 7, 2026(actual)
Against the original forecast
- Construction end4 months lateforecast Dec 31, 2025
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57417 in the federal list. How to read these figures.