Town of Unity 1st Avenue West Water and Waste Water Transmission Line Replacement

Unity, Saskatchewan

completeDrinking WaterGIS
Federal contribution
$1.7M
$1,676,036
Federal share40%

of $4.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 23, 2021
20212022202320242025
Built

Approved 6 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Unity
Construction start
May 1, 2023(actual)
Construction end
Jun 30, 2025(actual)

Against the original forecast

  • Construction end9 months earlyforecast Mar 31, 2026