Back to projects

Village of Ceylon - Water Treatment Plant Upgrades

Ceylon, Saskatchewan

completeDrinking WaterGIS
Federal contribution
$119,721
Federal share40%

of $299.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2021
20212022202320242025
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Ceylon
Construction start
Nov 14, 2023(actual)
Construction end
Mar 31, 2025(actual)

Against the original forecast

  • Construction start2 months lateforecast Sep 11, 2023
  • Construction end3 months lateforecast Dec 31, 2024

Also in Ceylon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57422 in the federal list. How to read these figures.