Village of Vanguard - Upgrading the Distribution of Pumps at the Water Treatment Facility
Federal contribution
$80,578
Federal share40%
of $201.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 9, 2021
20212022202320242025
Built
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Vanguard
- Construction start
- Aug 29, 2022(actual)
- Construction end
- Dec 4, 2024(actual)
Against the original forecast
- Construction end4 months earlyforecast Mar 31, 2025
Also in Vanguard
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57423 in the federal list. How to read these figures.