Buffalo Pound Water - Plant Renewal
Moose Jaw No. 161, Saskatchewan
Federal contribution
$89.1M
$89,132,108
Federal share40%
of $222.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 8, 2021
20222023202420252026
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Buffalo Pound Water Treatment Corporation
- Construction start
- Jun 6, 2022(actual)
- Construction end
- Apr 10, 2026(actual)
Against the original forecast
- Construction start3 weeks lateforecast May 16, 2022
- Construction end3 months lateforecast Dec 31, 2025
Also in Moose Jaw No. 161
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57425 in the federal list. How to read these figures.