Village of Holdfast - Water Treatment Plant Upgrades

Holdfast, Saskatchewan

completeDrinking WaterGIS
Federal contribution
$277,350
Federal share40%

of $693.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 9, 2021
20212022202320242025
Built

Approved 2 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Holdfast
Construction start
Nov 22, 2022(actual)
Construction end
Nov 20, 2024(actual)

Against the original forecast

  • Construction end4 months earlyforecast Mar 31, 2025

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57428 in the federal list. How to read these figures.