Resort Village of Coteau Beach Community Centre Construction

Coteau Beach, Saskatchewan

completeCultureRNIS
Federal contribution
$38,208
Federal share40%

of $95.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 9, 2021
2022
Built
Program
Rural & Northern Infrastructure Stream
Construction start
May 1, 2021(actual)
Construction end
Nov 16, 2022(actual)

Against the original forecast

  • Construction start8 months lateforecast Sep 1, 2020
  • Construction end4 months earlyforecast Mar 31, 2023

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57429 in the federal list. How to read these figures.