Lac la Ronge Area Landfill Decommissioning and Solid Waste Management Sites
Federal contribution
$1.5M
$1,479,380
Federal share40%
of $3.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 23, 2021
today
202220232024202520262027
BuiltForecast
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Northern Saskatchewan Administration District
- Construction start
- Jul 4, 2022(actual)
- Construction end
- Mar 31, 2027(forecast)