Back to projects

Town of Spiritwood - Sewage Pumping Station Replacements

Spiritwood, Saskatchewan

completeWastewaterGIS
Federal contribution
$844,800
Federal share40%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2021
202120222023
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Spiritwood
Construction start
Jul 15, 2021(actual)
Construction end
Mar 13, 2023(actual)

Against the original forecast

  • Construction start14 months lateforecast May 4, 2020
  • Construction end6 months lateforecast Aug 31, 2022

Also in Spiritwood

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57432 in the federal list. How to read these figures.