Town of Grenfell - Grenfell Secondary Lagoon Upgrade
Federal contribution
$785,200
Federal share40%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 23, 2021
202120222023202420252026
Built
Approved 9 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Grenfell
- Construction start
- Jun 14, 2021(actual)
- Construction end
- Oct 29, 2025(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 3, 2021
- Construction end7 months lateforecast Mar 31, 2025
Also in Grenfell
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57433 in the federal list. How to read these figures.