Town of Delisle Splash Park
Federal contribution
$123,930
Federal share40%
of $309.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 9, 2021
202120222023
Built
Approved 3 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Delisle
- Construction start
- Aug 3, 2021(actual)
- Construction end
- Dec 8, 2022(actual)
Against the original forecast
- Construction start14 months lateforecast Jun 1, 2020
- Construction end2 months lateforecast Sep 30, 2022