Village of Glen Ewen - Water Treatment Plant Expansion

Glen Ewen, Saskatchewan

completeDrinking WaterGIS
Federal contribution
$150,543
Federal share40%

of $376.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 23, 2021
202120222023
Built

Approved 6 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Glen Ewen
Construction start
Jun 1, 2022(actual)
Construction end
Apr 3, 2023(actual)

Against the original forecast

  • Construction end3 months lateforecast Dec 29, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57441 in the federal list. How to read these figures.