Village of Borden - Sewage Lift Station Upgrade
Federal contribution
$100,813
Federal share40%
of $252.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 9, 2021
20212022
Built
Approved 2 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Borden
- Construction start
- Apr 11, 2022(actual)
- Construction end
- Aug 31, 2022(actual)
Against the original forecast
- Construction start20 months lateforecast Aug 1, 2020
- Construction end2 months lateforecast Jun 30, 2022
Also in Borden
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57445 in the federal list. How to read these figures.