Kronau Community Recreation Cooperative Outdoor Skating Rink Revitalization
Hamlet of Kronau, Saskatchewan
Federal contribution
$56,247
Federal share40%
of $140.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 9, 2021
2021202220232024
Built
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Kronau Community Recreation Cooperative
- Construction start
- Oct 31, 2021(actual)
- Construction end
- Dec 23, 2023(actual)
Against the original forecast
- Construction start6 months lateforecast May 1, 2021
- Construction end3 months earlyforecast Mar 31, 2024
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57449 in the federal list. How to read these figures.