Village of Abbey Playground Revitalization

Abbey, Saskatchewan

completeRecreationCCRIS
Federal contribution
$40,160
Federal share40%

of $100.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 9, 2021
20212022
Built

Approved 3 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Village of Abbey
Construction start
Sep 1, 2021(actual)
Construction end
Dec 16, 2021(actual)

Against the original forecast

  • Construction end6 weeks lateforecast Nov 1, 2021