City of Melville - Wastewater Treatment System Expansion
Federal contribution
$4.3M
$4,320,560
Federal share40%
of $10.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 27, 2022
2022202320242025
Built
Approved 8 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Melville
- Construction start
- Jul 1, 2022(actual)
- Construction end
- Sep 9, 2025(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 27, 2022
- Construction end6 weeks lateforecast Jul 31, 2025